IHC Robbin’s involvement in Iluka’s JAA mine began during the Definitive Feasibility Study providing practical engineering design and tailored capital estimates for specific plant areas of the Wet Concentrator Plant (WCP). Design included life of mine field pumping scenarios for the transfer of mine head feed, process water and modified co-disposed tailings.

It was identified early in the study that the physical separation of the Jacinth and Ambrosia ore bodies coupled with diesel generated power presented difficult challenges not normally encountered in typical Mineral Sands broad acre deposits. IHC Robbins methodical and innovative approach ensured that these challenges were met enabling a solid platform and responsible project budget before the execution of the detailed design phase, in which IHC Robbins were allocated the process plant Structural, Mechanical, Pumping and Piping scope of works.

Tailored pipeline design and efficient pump motor selections were deemed critical to ensure an economic balance between capital and operating costs were maintained.

Specialised equipment, such as; skiddable field pumping stations, a robust process water pumping station and a circular plant water bin coupled with a lightweight WCP Pipe gantry were some of the innovations IHC Robbins contributed to the project.

IHC Robbins innovative design, methodical approach and dedication to excellent outcomes resulted in a successful project delivered on time and on budget.

 

Location:     Eucla Basin | South Australia

Client:         Iluka Resources Ltd

Services:      Engineering, Detail, Design